Progress at Platt

Having won the £4.6m contract to build the new 1FE Platt CoE Primary School close to the existing school on the A25 near Sevenoaks, site set up is now complete with Heras fencing installed around the site (apart from the front elevation where we have used solid wood hoardings). Metal gates have been installed for vehicular access and a pedestrian gate has been positioned in the hoarding.

The site cabins are all in place, connections to main services have been taken from the village hall and ducting has been installed within the car park for new services. Elsewhere, the main sewer connection is complete, the first site manhole has been installed and we have completed the installation of the surface water attenuation tank to the bottom of the site. Commencement of the cut and fill of the site has begun and will progress in several stages; currently we have completed 3 of the 7 stages.