Eight weeks in and the refurbishment project at Grade II Listed Hastings Central Library is taking shape.  With the enabling and demolition works now complete, the M&E first fix is underway and we have numerous trades working in tandem across all 5 floors. Secured under the Sussex Cluster Framework, the £3m works package entails the sympathetic improvement and modernisation of the library, retaining and protecting  heritage features including window frames and bannisters.